Flyvbjerg 2002: The Study Behind "Nine in Ten Projects Run Over Budget"

The first statistically significant study of cost overrun in transport infrastructure. This page gives the sample, the headline numbers by mode, the methodology, and the canonical citation so you can use the figures with confidence.

What is the Flyvbjerg 2002 study?

"Underestimating Costs in Public Works Projects: Error or Lie?" (Flyvbjerg, Holm & Buhl, 2002) was the first statistically significant study of cost escalation in transport infrastructure. It examined 258 projects worth about US$90 billion, built across 20 nations between 1927 and 1998. Actual costs exceeded the estimate in 86% of cases: rail ran 44.7% over on average, fixed links (bridges and tunnels) 33.8%, and roads 20.4%. Accuracy showed no improvement across the seventy years, which led the authors to conclude that underestimation is driven by strategic misrepresentation, not honest error.

258
transport projects, 20 nations, 1927-1998
86%
of projects had actual costs above the estimate
+44.7%
average rail cost escalation (the highest mode)
70 yrs
of data with no improvement in accuracy

Average cost escalation by transport mode

Project typeMean cost escalationStandard deviation
Rail+44.7%38.4
Fixed links (bridges and tunnels)+33.8%62.4
Roads+20.4%29.9
All projects (average actual vs estimate)+28%n/a

From Flyvbjerg, Holm & Buhl (2002), Table 1. Escalation is measured in real (inflation-adjusted) terms against the cost estimated at the decision to build. The standard deviations are as striking as the averages: they show that cost-overrun risk is not only large but highly variable, so an average figure understates the danger for any single project. Overruns ran roughly 65% higher for projects outside Europe and North America.


Sample and methodology

The sample is 258 transport infrastructure projects: rail, fixed links (bridges and tunnels) and roads, worth a combined US$90 billion in constant 1995 prices. The projects were built in 20 nations across Europe, North America and elsewhere, and completed between 1927 and 1998, giving roughly seventy years of coverage. It was, at publication, the first study of cost overrun in the sector large enough to draw statistically significant conclusions.

Cost overrun is defined as actual outturn cost minus estimated cost, in real terms, measured against the estimate made at the time of the decision to build. This is the same definition Flyvbjerg carried into his later 16,000-plus project database: it deliberately anchors to the figure used to justify the project, not to a later re-baselined budget, because re-baselining is one of the main ways overruns are hidden.

Because the estimate is taken at the decision to build, the finding is not simply that projects get more expensive. It is that the numbers used to approve them are systematically too low, and by a wide margin.


"Error or lie?" the study's central argument

The paper's title poses the question directly. If cost underestimation were honest error, you would expect it to be random (some projects over, some under) and to shrink over time as forecasting techniques improved. The data show neither. Underestimation is one-directional (costs are almost always too low, not too high) and it does not improve across the seventy-year window.

The authors conclude that the pattern is best explained by strategic misrepresentation: the political and organisational incentive to make a project look affordable enough to win approval. That argument is what later became the behavioural core of Flyvbjerg's work, from optimism bias and the planning fallacy through to the Iron Law of Megaprojects.


How this differs from the 16,000-project database

These are two different Flyvbjerg datasets that are often conflated. The 2002 study on this page is the original 258-project transport sample. The much larger figure people cite today, more than 16,000 projects across many sectors, comes from the database assembled later and summarised in How Big Things Get Done (Flyvbjerg & Gardner, 2023). If you need per-sector base rates (IT, nuclear, Olympics and so on), use the database page; if you need the seminal transport-cost-overrun finding, cite the 2002 study here.


How to cite

Flyvbjerg B., Skamris Holm M., Buhl S. (2002). Underestimating Costs in Public Works Projects: Error or Lie? Journal of the American Planning Association 68(3): 279-295.

Open-access author copy: arXiv 1303.6604 (read 8 October 2026). Publisher version: doi.org/10.1080/01944360208976273.

The paper is behind a publisher paywall at Taylor & Francis, but the authors' copy is freely downloadable from arXiv, so the figures here can be checked against the primary source: the 86% and 28% are in the results section, and the rail, fixed-link and road averages are in Table 1.


Related references on this site

Frequently Asked Questions

What is the Flyvbjerg 2002 study?

It is Flyvbjerg, Holm & Buhl (2002), 'Underestimating Costs in Public Works Projects: Error or Lie?', published in the Journal of the American Planning Association 68(3): 279-295. It was the first statistically significant study of cost escalation in transport infrastructure, based on 258 rail, bridge, tunnel and road projects worth about US$90 billion (1995 prices), built in 20 nations between 1927 and 1998. It is the empirical foundation for Flyvbjerg's later work on the Iron Law of Megaprojects and reference class forecasting.

How large were the average cost overruns in the study?

Average cost escalation was 44.7% for rail (standard deviation 38.4), 33.8% for fixed links such as bridges and tunnels (standard deviation 62.4), and 20.4% for roads (standard deviation 29.9). Across all 258 projects, actual costs were on average 28% higher than the costs estimated at the decision to build. The large standard deviations show that cost-overrun risk is both high on average and highly variable.

What share of projects came in over budget?

Cost was underestimated in 86% of the 258 projects, which is where the widely quoted 'nine out of ten projects run over budget' figure comes from. Overruns of up to 50% in real terms were common, and overruns above 50% were not uncommon. Cost underestimation was found for all project types, in all 20 nations, and across the whole 1927-1998 period.

Has cost-estimate accuracy improved over time?

No. The study found no sign that accuracy has improved over the roughly 70 years covered: cost underestimation was as prevalent for projects completed in the 1990s as for those completed decades earlier. On this evidence the authors concluded that persistent underestimation is best explained not by honest error or scaling problems but by strategic misrepresentation, that is, by political and organisational incentives to make projects look cheaper than they are.