BudgetOverrun.com is an independent reference site. Not affiliated with any PM software vendor. Statistics sourced from published research and cited throughout.

Budget Overrun Calculator: CPI, EAC, VAC, and TCPI

Free Earned Value Management calculator. Enter your project figures to calculate all primary EVM metrics and get an immediate RAG status assessment.

Quick-fill presets

Required Inputs

EAC Method + Optional


CPI Interpretation Guide

CPI RangeMeaningRecovery LikelihoodRecommended Action
CPI > 1.1Under budget, delivering more value per dollar than plannedN/A -- already aheadMaintain; consider whether estimates need revision
CPI 0.95-1.1On track -- normal performance bandHigh -- maintainNormal management; monthly review
CPI 0.8-0.95Minor overrun developingMedium -- corrective action neededIdentify cost drivers; scope review; increase reporting frequency
CPI 0.6-0.8Significant overrun -- project in troubleLow -- major intervention neededEscalate to sponsor; scope reduction; reforecast budget
CPI < 0.6Severe overrun -- project in jeopardyVery low -- consider project resetExecutive escalation; potential termination or full reset

PMI research: projects with CPI below 0.9 at the one-third completion mark rarely recover significantly. The final CPI tends to stay within 10% of the one-third milestone CPI.


EVM Formula Reference

CV (Cost Variance)
CV = EV - AC

Positive = under budget. Negative = over budget. Dollar amount of variance.

SV (Schedule Variance)
SV = EV - PV

Positive = ahead of schedule. Negative = behind schedule. Dollar amount of schedule variance.

CPI (Cost Performance Index)
CPI = EV / AC

For every $1 spent, you are delivering $[CPI] of planned value. CPI < 1 = over budget.

SPI (Schedule Performance Index)
SPI = EV / PV

For every $1 of planned progress, you have completed $[SPI] of work. SPI < 1 = behind schedule.

EAC (Estimate at Completion) -- Method 1
EAC = BAC / CPI

Assumes current cost efficiency will continue for the rest of the project. Most common.

EAC (Estimate at Completion) -- Method 2
EAC = AC + (BAC - EV)

Optimistic: assumes remaining work will be done exactly on budget.

VAC (Variance at Completion)
VAC = BAC - EAC

Projected surplus (positive) or overrun (negative) at project completion.

TCPI (To-Complete Performance Index)
TCPI = (BAC - EV) / (BAC - AC)

The CPI that must be achieved on all remaining work to finish on budget. TCPI > 1.2 is generally unachievable.

Frequently Asked Questions

What does a CPI of less than 1 mean?

CPI (Cost Performance Index) = Earned Value / Actual Cost. A CPI less than 1.0 means you are getting less than $1 of value for every $1 spent. CPI of 0.85 means: for every $1 spent, you have delivered $0.85 of planned work. PMI research shows that projects with CPI below 0.9 rarely recover significantly.

What is TCPI and what does a TCPI above 1 mean?

TCPI (To-Complete Performance Index) = (BAC - EV) / (BAC - AC). It answers: what CPI must we achieve on all remaining work to finish on budget? TCPI of 1.0 means remaining work must be done exactly on budget. TCPI of 1.1 means 10% more efficient than planned. TCPI above 1.2 is generally considered unachievable without a budget change.

What are the methods for calculating EAC?

The three primary EAC methods: (1) EAC = BAC / CPI -- assumes current efficiency continues (most common); (2) EAC = AC + (BAC - EV) -- optimistic, assumes remaining work on budget; (3) EAC = AC + ETC -- uses a new bottom-up estimate for remaining work (most accurate when circumstances have fundamentally changed). PMBOK 7 also defines EAC = AC + [(BAC - EV) / (CPI x SPI)].

What is BAC in EVM?

Budget at Completion (BAC) is the total authorized budget for a project -- the planned cost of all work. It is the baseline against which all EVM metrics are calculated. BAC is set at project start and should not change unless formally re-baselined through a change control process.

Deepen Your Knowledge

Didn't find your answer?

Ask us. A real person reads every question and we answer the ones we can, with sources. If your question would help other readers, we may publish an anonymised version, with your permission. General reference, not financial advice.

Updated 2026-06-13