IndependentBudgetOverrun.com is an independent reference site. No PM software vendor owns, sponsors or reviews it; one PM tool link is a labelled partner link.

What Is a Budget Overrun? And Why 43% of Projects Experience One

The independent reference for project budget overruns. Real data, cited sources, a working EVM calculator, and no vendor agenda.

What is a budget overrun?

A budget overrun is the amount by which a project's actual cost exceeds its approved budget, measured as Actual Cost minus Budget at Completion, or as a percentage of the original budget. Overruns are common: 43% of projects finish over their initial budget (PMI's 2018 survey found 57% finished within it), rising to almost 9 in 10 for transport infrastructure (Flyvbjerg, Holm & Buhl 2002) and 98% of megaprojects overrunning by more than 30% (McKinsey 2015). Each figure on this page links to the document that states it, with the date we read it.

43%
of projects finish over their initial budget (57% within it)
27%
average cost overrun for IT projects
80%
average cost increase across McKinsey's megaproject sample
McKinsey 2015, Exhibit 2, read 8 October 2026

Definition

A budget overrun occurs when the actual cost of a project exceeds the approved budget. It is measured as the difference between Actual Cost (AC) and Budget at Completion (BAC), expressed as an absolute figure or a percentage of the original budget.

Overrun % = (AC - BAC) / BAC x 100

Budget overrun vs cost escalation: These are commonly confused. A budget overrun is unexpected: the project costs more than planned due to poor estimation, scope changes, or execution failures. Cost escalation refers to anticipated cost growth, such as inflation adjustments written into contracts. Most overruns combine elements of both, but the distinction matters for contract law and accountability.

For a deeper treatment of what causes overruns, see causes of budget overruns. For EVM-based forecasting, see the EVM guide.

Quick EVM Check

Enter your project figures to get instant CPI and overrun forecast

Full calculator with CPI, SPI, EAC, VAC, TCPI · EAC calculator (4 methods)


Industry Overrun Rates at a Glance

Industry% Projects OverrunAvg Overrun %Source (document, date read)
Transportation infrastructure86% (almost 9 in 10)28%Flyvbjerg, Holm & Buhl 2002, read 8 October 2026
IT / Software71% challenged or failed45% (large IT)Standish CHAOS 2015, read 8 October 2026 / McKinsey-Oxford 2012, read 8 October 2026
Government IT (public sector)nearly 1 in 2~3x private sectorMcKinsey 2022, read 8 October 2026
Megaprojects (>$1B; mining, oil and gas, infrastructure)98% (overrun above 30%)80%McKinsey 2015, read 8 October 2026
All project types (16,000+ projects)91.5% miss budget or schedule52% miss budgetFlyvbjerg & Gardner 2023 (book; figure as quoted, not checked against the page)

Full statistics by sector and project size, each linked to its source document


Famous Budget Overruns

Space | USA

James Webb Space Telescope

Original budget$500M (1997 study)
Actual cost$9.66B (GAO 2021)
~1,830%over budget
Architecture | Australia

Sydney Opera House

Original budgetAUD 7M
Actual costAUD 102M
1,357%over budget
Infrastructure | USA

Boston Big Dig

Original budget$2.6B (1985)
Actual cost$14.8B (2007)
469%over budget

Full list of 12 historic overruns, each traced to an audit report or official document


Explore the Reference Library


Source-Cited Reference Pages

The landmark studies

All studies, compared ›

By industry

Methods to prevent overruns

Case studies

Frequently Asked Questions

What is a budget overrun?

A budget overrun occurs when the actual cost of a project exceeds the approved budget. It is measured as the difference between actual cost (AC) and the original budget (BAC). Unlike cost escalation, which refers to anticipated increases such as inflation, a budget overrun is unexpected and indicates the project is performing below plan.

What percentage of projects go over budget?

PMI's Pulse of the Profession 2018 survey of 4,455 practitioners found that 57% of projects finished within their initial budgets, so 43% did not. Rates vary by sector: costs were underestimated in almost 9 out of 10 transport infrastructure projects (Flyvbjerg, Holm and Buhl 2002, 258 projects), 98% of megaprojects overrun by more than 30% (McKinsey 2015), and the Standish Group's CHAOS 2015 report counts 71% of software projects as challenged or failed.

What is the difference between cost overrun and cost escalation?

A cost overrun is unexpected: the project costs more than planned due to poor estimation, scope creep, or execution problems. Cost escalation is anticipated growth in cost, such as known inflation adjustments or agreed scope additions. In contracts, escalation clauses may allow cost adjustments for inflation; overruns beyond those clauses are the contractor's or project's problem.

How do you calculate budget overrun?

Simple calculation: Budget Overrun = Actual Cost (AC) minus Budget at Completion (BAC). As a percentage: Overrun % = (AC - BAC) / BAC x 100. For a forward-looking forecast using Earned Value Management: EAC = BAC / CPI, where CPI = Earned Value / Actual Cost. A CPI below 1.0 means you are over budget for the value delivered.

See the cost overrun formula with worked examples, or use our free EVM calculator.

What is earned value management (EVM)?

Earned Value Management (EVM) is a project performance measurement method that integrates scope, schedule, and cost. The three core values are Planned Value (PV: work scheduled to be done), Earned Value (EV: work actually completed, valued at the budget rate), and Actual Cost (AC: what you spent). From these, you calculate CPI, SPI, EAC, VAC, and TCPI.

See our complete EVM guide for formulas and worked examples.

Didn't find your answer?

Ask us. A real person reads every question and we answer the ones we can, with sources. If your question would help other readers, we may publish an anonymised version, with your permission. General reference, not financial advice.

Updated 2026-10-08