How to Deal With a Project Cost Overrun
The project is already over budget. This is not about prevention -- it is about what to do next. A 7-step recovery playbook grounded in earned value, so the decision to recover, re-baseline, or de-scope is driven by numbers rather than optimism.
What to do when a project is over budget, in order
- Measure it -- compute CPI (EV / AC) so you know the true size of the overrun.
- Forecast it -- compute EAC (BAC / CPI) to see where the budget lands if nothing changes.
- Diagnose it -- separate scope growth, estimation error, and execution shortfall.
- Size the recovery -- compute TCPI to see the efficiency the rest of the work must hit.
- Decide -- recover, re-baseline, or de-scope. A TCPI far above your CPI means the original budget is gone.
- Rebuild and communicate -- re-baseline through governance and report the forecast honestly.
Run the numbers with the free EVM calculator (CPI, EAC, VAC, TCPI). New to these terms? Start with the earned value guide.
Measure the overrun precisely
Forecast where the budget actually lands
Diagnose the root cause
Calculate the recovery you would need
Choose the response: recover, re-baseline, or de-scope
Rebuild the plan and re-baseline formally
Communicate and capture the lessons
The four numbers a recovery decision turns on
| Metric | Formula | What it tells you |
|---|---|---|
| CPI -- Cost Performance Index | EV / AC | How much value each dollar is buying. Below 1.0 = over budget for value delivered. |
| EAC -- Estimate at Completion | BAC / CPI | Where the total cost lands if current efficiency holds. |
| VAC -- Variance at Completion | BAC - EAC | The forecast overrun in dollars. Negative = over budget. |
| TCPI -- To-Complete Performance Index | (BAC - EV) / (BAC - AC) | The efficiency the remaining work must hit to still finish on budget. Far above your CPI = recovery not realistic. |
These are standard earned-value formulas (PMBOK). For a worked walkthrough of each, see the complete EVM guide, or enter your own numbers in the calculator.
Frequently Asked Questions
What should you do first when a project goes over budget?
Measure the overrun precisely before you react. Compute the Cost Performance Index (CPI = EV / AC) and the forecast final cost (EAC = BAC / CPI). Only once you know the size and trajectory of the overrun should you decide whether to recover, re-baseline, or de-scope. Reacting before measuring is the most common early mistake.
How do you forecast the final cost of an overrunning project?
Use Estimate at Completion (EAC). The most defensible formula is EAC = BAC / CPI, which assumes the cost efficiency seen so far continues. If the overrun was a one-off that will not recur, use EAC = AC + (BAC - EV) instead. Forecasting both gives a realistic range, and VAC = BAC - EAC shows the projected overrun in dollars.
What is TCPI and how do I know if recovery is realistic?
The To-Complete Performance Index is the cost efficiency the remaining work must achieve to hit the original budget: TCPI = (BAC - EV) / (BAC - AC). If work to date ran at a CPI of 0.85 and the TCPI required is 1.15, the team would have to become roughly 35 percent more efficient than it has been. A TCPI materially above 1.0 (rule of thumb, above about 1.10) is rarely achievable without changing scope or baseline.
When should you re-baseline instead of trying to recover?
Re-baseline when the original budget is no longer achievable and reporting against it hides reality. Triggers: the required TCPI exceeds roughly 1.10, the cumulative CPI has been stable and below 1.0 for several periods, or scope has formally changed. Re-baselining is a sponsor-approved governance decision, not a way to erase a variance -- preserve the original baseline so the overrun stays visible for lessons learned.