IndependentBudgetOverrun.com is an independent reference site. No PM software vendor owns, sponsors or reviews it; one PM tool link is a labelled partner link.

HS2: How a £37.5bn National Railway Became a £100bn Stub

How much has HS2 cost so far?

£44.2bn had been spent on HS2 by 31 March 2026, in cash terms. Add the £2.6bn spent on the cancelled Phase 2 and the total is £46.8bn. That is roughly 39% to 47% of the £94.3bn to £112.4bn the whole programme is now expected to cost in cash.

Source: Department for Transport, HS2 six-monthly report to Parliament, 19 May 2026 (financial annex), the latest published as of 17 November 2026. The percentage is our division of the two published cash figures.

HS2 is the clearest live example of the Iron Law of Megaprojects in Britain. It was sold in 2009 as a £37.5bn national network reaching Manchester and Leeds. The northern legs were cancelled, yet the surviving London-Birmingham section alone is now estimated at £87.7bn to £102.7bn, and first trains have slipped from 2026 to somewhere between 2036 and 2039.

How much has HS2 gone over budget?

The full HS2 network was estimated at £37.5bn (2009 prices). After the Manchester and Leeds legs were cancelled, only London to Birmingham remains, and in May 2026 the Department for Transport estimated that single section at £87.7bn to £102.7bn (2025 mixed price base). That is roughly double its own 2020 funding envelope of £44.6bn, and up to about 2.7 times the original full-network figure for a fraction of the route.

£87.7-102.7B
London-Birmingham estimate, mixed price base
DfT, May 2026
£44.2B
spent so far (cash), to 31 Mar 2026; £46.8B with former Phase 2
DfT six-monthly report, May 2026
£37.5B
original full-network estimate
2009 prices
2036-2039
first services (original target: 2026)
Old Oak Common to Birmingham

The cost history, step by step

HS2's numbers are easy to misread because the price base and the scope both keep changing. The honest way to read them is to hold the two comparisons separate: what the whole network was meant to cost, and what the surviving Phase 1 was meant to cost on its own.

DateScopeEstimate (price base)
2009Full Y-network (London-Birmingham-Manchester-Leeds)£37.5bn (2009)
2013Full network£50.1bn (2011)
2015Full network (funding envelope)£55.7bn (2015)
2019Full network (Oakervee / Cook stocktake)£72bn-£98bn (2015)
Apr 2020Phase 1 (London-Birmingham) Notice to Proceed£40.3bn target, £44.6bn envelope (2019)
Oct 2023Phase 2 (Birmingham-Manchester) cancelled; London-Birmingham only-
May 2026Phase 1 (London-Birmingham) only, post-reset£87.7bn-£102.7bn (2025)

Two things stand out. The route got shorter, losing the entire northern half, while the cost of what is left more than doubled its 2020 funding envelope. And the single London-Birmingham line now costs more than the whole national network was ever supposed to.


How much has HS2 cost so far?

The forecasts above are the expected final bill. The money actually spent is smaller. The Department for Transport's six-monthly report to Parliament of 19 May 2026 puts spending on the HS2 programme at £44.2bn to the end of March 2026, in nominal (cash) prices, including land and property. A further £2.6bn was spent on the former Phase 2 before it was cancelled, which brings the overall total to £46.8bn. Of the programme's £44.2bn, civil engineering (tunnels, viaducts, earthworks) took the largest share:

What the money went onSpent to 31 Mar 2026 (cash)
Civils (tunnels, viaducts, earthworks)£31.2bn
Stations£4.8bn
Indirects (programme overheads)£4.1bn
Land and property£3.7bn
Railway systems£0.3bn
HS2 programme total£44.2bn
Former Phase 2 (cancelled)£2.6bn
Overall total£46.8bn

The department rounds each line to one decimal place of a billion, so the lines do not always add exactly. Land and property includes a £0.5bn provision for land the department is obliged to buy.

How the spend to date has grown

Spent to the end ofHS2 programme, cashReported in
April 2025£40.5bnDfT report, July 2025
February 2026£43.6bnDfT report, March 2026
March 2026£44.2bnDfT report, May 2026

The department now reports spend in cash, after committing to the Public Accounts Committee to express costs in a more current price base. Earlier reports gave spend to date in 2019 prices, so older totals are not comparable with this table. The programme's budget for 2026 to 2027 is £7.1bn.

How much of HS2 is left to pay for?

Spend to date is in cash, so compare it with the forecast in cash. The May 2026 report gives a provisional cash estimate for the whole programme, including projected inflation, of £94.3bn to £112.4bn. Our arithmetic on those published figures:

If the final cash cost isShare spent (£44.2bn)Still to spend
£94.3bn (low end)47%£50.1bn
£112.4bn (high end)39%£68.2bn

The department says the same in words: the years left to finish are "roughly the same as when construction started in 2020, and it is likely we will need to spend the same amount as has already been spent to date." Do not subtract the spend from the £87.7bn to £102.7bn headline range: that range mixes cash already spent with future costs at Q3 2025 prices, so it is not a cash total.


Which HS2 cost figure answers your question?

HS2 has six official cost figures in common use, each on a different basis. Pick the one that matches your question:

Your questionFigure to useBasis
How much has been spent so far?£44.2bn (£46.8bn with former Phase 2)Cash, to 31 Mar 2026
What will London-Birmingham cost?£87.7bn to £102.7bnMixed: cash to date plus Q3 2025 prices, no future inflation
What will the final cash bill be?£94.3bn to £112.4bnCash, including projected inflation (provisional)
How far over the 2020 budget is it?£70.9bn to £82.2bn against £44.6bn (59% to 84% over)Both in 2019 prices
What is HS2 Ltd aiming for?£93.2bnChief executive's target, in the lower half of the headline range
What was it first meant to cost?£37.5bnFull network to Manchester and Leeds, 2009 prices

The 59% to 84% is our arithmetic: the May 2026 forecast restated in 2019 prices, divided by the £44.6bn Phase One budget (including Euston) that the department reported at the start of construction, also in 2019 prices.


How we sourced these figures

Every current cost on this page comes from a Department for Transport report to Parliament, re-read on 17 November 2026. Spend to date, the 2026 to 2027 budget, the cash estimate, the 2019-price range and the £93.2bn target are from the May 2026 six-monthly report and its financial annex. The earlier spend totals are from the July 2025 and March 2026 reports, and the £44.6bn 2020 budget is from the March 2021 report. Where we compare two figures (share spent, money still to spend, percentage over budget) we only divide or subtract figures on the same price base, and we say so beside the result.


Why the cost rose

The National Audit Office and successive government reviews point to a consistent set of causes, most of them textbook optimism bias and strategic misrepresentation of the kind reference class forecasting is meant to correct:

  • Politically low initial estimates. The early figures were set to secure approval, not to survive contact with the engineering. This is the same pattern the NAO identified on Crossrail and the Big Dig.
  • Underestimated works. Tunnelling, viaducts such as the Colne Valley (Britain's longest railway bridge), and the scale of environmental and planning mitigation all cost far more than the business case assumed.
  • Delivery inefficiency. The May 2026 reset attributed a large share of the increase to inefficiency within HS2 Ltd and its supply chain, alongside weak cost control.
  • Inflation not captured. Earlier forecasts did not consistently reflect construction inflation, so real cost growth was masked until it was re-based upward.

A fundamental reset of the programme began in June 2025 under a new chief executive; the May 2026 Accounting Officer assessment is the first full re-baselining to come out of it.


What HS2 teaches about budget overruns

HS2 is a live illustration of Bent Flyvbjerg's Iron Law of Megaprojects: over budget, over time, over and over again. It also shows why the choice of baseline matters so much. Cutting scope did not cut cost, because the fixed early works, the tunnels and the reset overheads all stayed. Anyone forecasting a project of this class should have started from the reference class of comparable rail megaprojects, where a 40%-plus real cost overrun is the base rate, not the worst case.


Sources

Related

Frequently Asked Questions

How much has HS2 gone over budget?

HS2 was first estimated at £37.5bn (2009 prices) for the full Y-network linking London, Birmingham, Manchester and Leeds. The northern legs were cancelled in stages, and since October 2023 only London to Birmingham survives. In May 2026 the Department for Transport put the cost of that single remaining section at £87.7bn to £102.7bn (a mixed 2025 price base). That is roughly double its own 2020 funding envelope of £44.6bn (2019 prices), and up to about 2.7 times the original full-network estimate for a fraction of the railway.

How much has HS2 cost so far?

To 31 March 2026, £44.2bn had been spent on the HS2 programme in nominal (cash) prices, according to the Department for Transport's six-monthly report to Parliament of 19 May 2026. A further £2.6bn was spent on the cancelled Phase 2, so the overall total is £46.8bn. The same report gives a provisional cash estimate of £94.3bn to £112.4bn for the whole programme, so on a like-for-like cash basis about 39% to 47% has been spent. The department's own words: it is likely the programme will need to spend the same amount again as has already been spent.

How much is HS2 over budget in like-for-like prices?

When construction started in 2020 the budget for Phase One, including Euston, was £44.6bn in 2019 prices. The Department for Transport's May 2026 report restates the current forecast in the same 2019 prices as £70.9bn to £82.2bn, which is 59% to 84% over that budget. On the department's headline basis (cash already spent plus remaining costs at Q3 2025 prices, excluding future inflation) the forecast is £87.7bn to £102.7bn.

How much will HS2 spend in 2026-27?

The HS2 programme's budget for the 2026 to 2027 financial year is £7.1bn in nominal prices, with a further £0.1bn for closing out the former Phase 2, according to the financial annex of the Department for Transport's May 2026 report to Parliament.

Why did HS2 cost so much more than planned?

The National Audit Office and successive government reviews attribute the growth to optimistically low initial estimates set for political approval, underestimation of the engineering work (tunnelling, viaducts and environmental mitigation), inefficiency within HS2 Ltd and its supply chain, scope and specification changes, and inflation that earlier forecasts did not consistently capture. A June 2025 reset under a new chief executive re-baselined the programme upward again.

When will HS2 open?

The May 2026 Accounting Officer assessment expects first services between Old Oak Common in west London and Birmingham Curzon Street to begin between May 2036 and October 2039. Services into the London terminus at Euston, via Handsacre Junction to the north, are expected between May 2040 and December 2043. The original target was 2026.

Didn't find your answer?

Ask us. A real person reads every question and we answer the ones we can, with sources. If your question would help other readers, we may publish an anonymised version, with your permission. General reference, not financial advice.

Updated 2026-11-17